Modifying the Priority of Operating Procedures

When an event occurs in the system, it may match the filter conditions of more than one operating procedure. However, only one procedure at a time can execute in assisted treatment, so that the one with the highest priority will run.

  • System Manager is in Engineering mode.
  1. In System Browser, select Management View.
  1. Select Project > System Settings > Operating Procedures.
  1. In the Operating Procedures tab, select an operating procedure in the list and do one of the following:
  • Click Priority and enter a new value.
    NOTE: Zero is the highest priority. The system does not allow giving the same priority to two procedures.
  • Click Move Up or Move Down.
    NOTE: The topmost procedure has the highest priority.
  1. Click Save .