Align a Client/FEP Project with the Server Project

For a Server project which is linked to a Client/FEP project, you have changed the security settings for the proxy port, Client/Server communication mode, Certificate type, removed an extension from a project and so on. Use the following procedure to align the Client/FEP project with the changed settings of the selected Server project.

  • The Client/FEP project that you want to re-align with the modified Server project is Stopped.
  1. In the SMC tree, select Projects > [project].
  1. Click Edit .
  1. Click Realign Server Configuration .
  1. Click Save Project .
  • The project on Client/FEP is re-aligned with the modified Server project.