- Stop a Project
Stop a Project
- At least one project is available under the Projects node and is
Started
.
- In the SMC tree, select Projects > [project].
- Click the Project Settings tab.
- Click Stop .
- Click OK.
- In the Server Project Information expander of the Project Settings tab, the project status indicator icon changes to black and not animated indicating that the project is stopped.
The Pmon service for the project in the Windows services is Stopped
.
The Desigo CC client is disconnected or does not launch and you cannot proceed with the normal engineering configurations.